Our Solution
Instead of initiating another supplier search, we performed a comprehensive engineering-led Design for Manufacturing (DFM) assessment.
- Our team identified critical deviations between the design drawings and applicable manufacturing standards and recommended engineering modifications that significantly improved manufacturability.
- Gear manufacturing methodology
- Machining sequence
- Heat treatment process
- Grinding operations
- Surface finish requirements
- Critical-to-Quality (CTQ) controls
- Process capability and inspection methodology
- Working collaboratively with the customer and the selected supplier, we successfully industrialized the complete 7-gear transmission set within 4 months, well ahead of the revised project schedule.